Dismantling and transportation of Efes brewery barrels
-
Project location:
Moscow
Back
The pile was fully assembled up to 80 meters on the ground. After that it was lifted by a Liebherr LR 1750 crawler crane onto a mobile self-propelled unit. Specialists checked the position of the exposed support and then loaded it into the sea with a vibropiling machine.
A total of eight pipe piles will be loaded on this support using the technology that allows to significantly reduce the time of the support construction. Then the builders will start similar works on the neighboring supports of the road bridge.